27 May 2022
This article is intended to provide a general introduction to FIDIC contracts and their management and administration. FIDIC is an organization comprising Engineer’s from around the world, from Contractors, Consultant’s and Employer’s
Its title translates from French to English as “The International Federation of Consulting Engineers” and it is generally recognized as the world’s leading publisher of Construction Contracts
It is the Contract of choice of most Asian Governments and many private Employers. FIDIC publishes a wide range of standard contracts, providing for the following construction related situations
FIDIC has always used a color code system to identify and distinguish its Contracts. Over the years various contract editions have been published, which are best summarized as pre and post-1999
Pre 1999
Red Book – 1987 4th Edition – Traditional Employer Design Contract for Civil Works
Orange Book – 1995 1st Edition – Design Build Contract
Post 1999
Red Book – 1st Edition – Traditional Employer Design Contract for Civil Works
Yellow Book – 1st Edition – Design Build Contract
Silver Book – 1st Edition – EPC Contract
At present, the most common forms used are the Red Books (Both the 1987 4th Edition and the 1999 1ST Edition). In recent years it is noticeable that the 1999 1st Editions is being more widely used. However, in recent years large projects are often using the new Yellow and Silver Book Contracts.
FIDIC Contracts are generally accepted in their base form to represent a fair sharing of construction risks between the Contractor and the Employer.
Firstly, let's look at the Red Book
The Red Book, both the 1987 4th Edition and the 1999 1st Edition are suitable for Traditional Civil Engineering Projects for which the design is prepared by the Employer
The Key Principles of both Contracts are
Both Contracts provide for the following
The key differences between the 1987 4th Edition and the 1999 1st Edition can be summarized as follows
1987 4th Edition | 1999 1st Edition |
72 Base Clauses and in places complex legal language | 20 Base Clauses with the simplified language used |
Engineer required to be impartial (to act for both the Contractor and Employer equally) | The Engineer shall act on behalf of the Employer |
Late issue of cost and time does not mean loss of entitlement for the Contractor | Late Issue of cost and time notices means loss of entitlement for the Contractor |
Dispute Resolution by Arbitration | Dispute Resolution by DAB ( Dispute Adjudication Board ) first and then if necessary by Arbitration |
n/a | Employer to provide proof of Financial Capability |
n/a | Employer can make claims against the Contractor and deduct amounts from payments |
n/a | Adverse site condition claims can be offset by benefit of more favorable conditions in other areas of the site |
In terms of the 1987 4th Edition, the key clauses and issues of note are considered to be
Clause No. | Clause Title |
Summary of key issue
|
1.1(g) (i) | Definitions |
Cost claim entitlement excludes right to profit cost/time |
6.3 & 6.4 |
Disruption of Progress / Delay of Drawings
| Contractor entitled to additional costs and time for late issue of drawings etc |
44 | Extension of Time |
Contractor to give notice of project delay within 28 days
|
51 | Variations |
Contractor to inform Engineer if new rates are required for variations
|
53 | Procedure for Claims |
Contractor to inform Engineer of claims for additional payment with initial notice within 28 days
|
In terms of the 1999 1st Edition, the key clauses are considered to be
Clause No. | Clause Title |
Summary of key issue
|
1.1.4.3 | Definitions |
Cost claim entitlement excludes right to profit
|
1.9 |
Disruption of Progress / Delay of Drawings
| Contractor entitled to additional costs and time for late issue of drawings etc |
5.2 | Nominated Subcontractors |
Contractor can object to Subcontractors nominated by the Employer
|
12 | Measurement and Evaluation |
Conditions for new unit rates for remeasurement and variations
|
19 | Force Majeure |
Wide ranging Force Majeure Definition and clear cost / time entitlement but the vent must prevent substantial performance.
|
20 | Claims |
Contractor must give notice of cost / time claims within 28 days
|
Next a brief look at the Yellow and Silver Books . The Yellow Book is for Design and Build Projects and is essentially the same as the Red Book with the exception of
The Silver Book is for EPC / Turnkey Projects and is essentially the same as the Red and Yellow Books with the exception of
In terms of the general administration of FIDIC Contracts, the following are considered the key issues
PRE CONTRACT TENDER STAGE
POST CONTRACT EXECUTION STAGE
CONCLUSION AND CLOSING
Since most of our projects will involve the use of a FIDIC Contract or similar clauses it’s important for us to understand their principles and key aspects, and requirements
It is hoped that this presentation has given you an introduction to these issues and has stimulated your interest to research them in more detail
Author: James Bristow